Corpfin Mod 4 npv irr 3 projects practice exam question


Corpfin Mod 4 npv irr 3 projects practice exam question

Author
Message
NEAS
Supreme Being
Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)

Group: Administrators
Posts: 4.5K, Visits: 1.6K

Corpfin Mod 4 npv irr 3 projects practice exam question

A firm has three projects (S = short; M = medium; L = long), each with an opportunity cost of capital of 11.3% and one initial investment at time t=0. The initial investment differs for the three projects.

●    Project S has one cash inflow of 1,846.00 at time t=1.
●    Project M has cash inflows of 392.00 each at times t=1 and t=2.
●    Project L has cash inflows of 548.00 each at times t=1, t=2, and t=3.

❏    Projects S and M have the same IRR.
❏    Projects S and L have the same NPV.

The IRR of Project L is 15.9%.

Question 1.2: What is the initial investment (at time t=0) of project L?


Answer 1.2: The cash flows for Project L are the initial investment at time t=0 and cash inflows of 548.00 each at times t=1, t=2, and t=3. The IRR of Project L is 15.9%. We solve for the initial investment Z:

Z = 548 / 1.1591 + 548 / 1.1592 + 548 / 1.1593 = 1,232.77


Question 1.3: What is the NPV of Projects L and S?


Answer 1.3: The opportunity cost of capital is 11.3%. For project L, the initial investment is 1,232.77 at time t=0 and the cash inflows are 548.00 each at times t=1, t=2, and t=3. The NPV of the project is

    – 1,232.77 + 548 / 1.113 1 + 548 / 1.1132 + 548 / 1.1133 = 99.43

Project S has the same NPV.


Question 1.4: What is the initial investment of Project S?

Answer 1.4: The NPV of Project S is 99.43 and it has one cash inflow of 1,846.00 at time t=1. The initial investment of Project S satisfies

initial investment + 1,846.00 / 1.113 1 = 99.43

➾ initial investment = 99.43 – 1,846.00 / 1.113 1 = (1,559.15), or a cash outflow of 1,559.15.




Question 1.5: What is the IRR of Projects S and M?

The IRR of Project S satisfies 1,559.15 × IRR = 1,846.00, so
    
IRR = 1,846.00 / 1,559.15 – 1 = 18.398%


Project M has the same IRR.


Question 1.6: What is the initial investment of Project M?

Using the IRR of 18.398% for Project M and the cash inflows of 392.00 each at times t=1 and t=2, we derive the initial investment as

    392 / 1.18398 1 + 392 / 1.183982 = 610.73


Question 1.7: What is the NPV of Project M?

Answer 1.7: The opportunity cost of capital is 11.3%. For project M, the initial investment is 610.73 at time t=0 and the cash inflows are 392.00 each at times t=1 and t=2. The NPV of the project is

    – 610.73 + 392 / 1.113 1 + 392 / 1.1132 = 57.91

Attachments
GO
Merge Selected
Merge into selected topic...



Merge into merge target...



Merge into a specific topic ID...





Reading This Topic


Login
Existing Account
Email Address:


Password:


Social Logins

  • Login with twitter
  • Login with twitter
Select a Forum....











































































































































































































































Neas-Seminars

Search