debt tax shield adjusted present value practice exam question


debt tax shield adjusted present value practice exam question

Author
Message
NEAS
Supreme Being
Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)Supreme Being (5.9K reputation)

Group: Administrators
Posts: 4.5K, Visits: 1.6K

BM Chapter 19 debt tax shield adjusted present value practice exam question.

A firm undertakes a one year project on January 1 with the following attributes:

●    The initial investment is 2,016.
●    The project provides an expected return of 2,244 at the end of the year (December 31).

●    The opportunity cost of capital is 9.4% per annum.
●    The return on debt rD is 6.3% per annum.
●    The debt to value ratio (D/V) is 34.2%.
●    The corporate tax rate is 28.4%.

Question 19.1: Base case net present value of the project

What is the base case net present value of the project?

Answer 19.1: The initial investment is 2,016, the project provides an expected return of 2,244 at the end of the year, and the opportunity cost of capital is 9.4% per annum. The base case net present value of the project is –2,016 + 2,244 / (1 + 9.4%) = 35.19.



Question 19.2: Value of debt tax shield

What is the value of each dollar of debt tax shield when the tax is paid?

Answer 19.2: The corporate tax rate is 28.4%, and the return on debt rD is 6.3% per annum. The value of each dollar of debt tax shield is 28.4% × 6.3% = 1.79%.



Question 19.3: Present value of debt tax shield

What is the present value of the debt tax shield?

Answer 19.3: The corporate tax rate is 28.4%, the return on debt rD is 6.3% per annum, the initial investment is 2,016, and the debt to value ratio (D/V) is 34.2%. The value of the debt tax shield one year from now is 28.4% × 6.3% × 2,016 × 34.2% = 12.34. The present value of the debt tax shield is

    (28.4% × 6.3% × 2,016 × 34.2%) / (1 + 6.3%) = 11.60.


Question 19.4: Adjusted present value of the project

What is the adjusted present value of the project?

Answer 19.4: the adjusted present value of the project is the base case net present value of the project + the present value of the debt tax shield = 35.19 + 11.60 = 46.79.

Attachments
GO
Merge Selected
Merge into selected topic...



Merge into merge target...



Merge into a specific topic ID...





Reading This Topic


Login
Existing Account
Email Address:


Password:


Social Logins

  • Login with twitter
  • Login with twitter
Select a Forum....











































































































































































































































Neas-Seminars

Search